At the France-Fujairah Forum, Fujairah Municipality’s Chief Engineer, Sohail Iqbal, gave a keynote address on Fujairah’s big projects that are fuelling the emirate’s expansion.
An important part of the jig-saw puzzle is the Fujairah Northern Land Reclamation Project (FNLRP). Here are the basic pointers:
Location: Fujairah, UAE, north of the Fujairah Port.
Client: The Government of Fujairah.
Date of Completion: Phase 1-August 2011.
MUC Role: Consultant and Supervisor.
The reclamation and coastal protection of 224 ha. of land will stretch 500m from the coastline into the sea.
Purpose
The reclaimed area will be used for oil storage facilities, expansion of the port and other industrial developments.
Timetable
There are two phases to the project and three parts to the second phase.
FNLRP—Phase 2/Lot 1
This phase is to be completed by May 2012.
FNLRP—Phase 2/Lot 2
This part of the project is to be completed by December 2012.
FNLRP—Phase 2/Lot 3
This part of the project is to be completed by December 2012.
Other Major Fujairah Projects
The Abu Dhabi Crude Oil Pipeline Project in Fujairah—Latest News, FIF, 10 October 2011.
The Fujairah Oil Industry Zone-Latest News, FIF, 9 October 2011.
The Developments at the Fujairah Port—Latest News, FIF, 8 October 2011.
Strategic Grain Terminal in Fujairah—Latest News, FIF, 6 October 2011.
Sheikh Khalifa Bin Zayed Highway Between Dubai and Fujairah-Latest News, FIF, 5 October 2011.
France—Fujairah Forum
Several articles have been posted on this France-Fujairah business forum, held in Fujairah on 29 September 2011. Go to this article and follow the links that it includes.
Geoff Pound
More Fujairah news, information, photos and videos are posted on the Fujairah in Focus Facebook Page.
Images: The points and photos are drawn from Sohail Iqbal’s Powerpoint Presentation and are used with thanks.
No comments:
Post a Comment
Note: Only a member of this blog may post a comment.